Hi Experts,

How to transport the factory calendar . According to Note 86621 - Calendar: Change or transport is not possible and Note 538344 - Transporting calendar dates says can be transported.

Can any body tell the steps / Process to transport the new factory calendar created in development system to Production system.

Regards

Ram

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

ask Basis guy to open PRD client & do the changes in factory calender directly in PRD system.

reg,

Deepak

Former Member
0 Kudos

Hi,

You can use maual transport request to transport the factory calender.

Create a new empty request in SE09

Then you can manually assign the key fields of the change in the object list and then can move the changes.