HI Guru's
I am currently on the ETO based project where in on a particular WBS i may have no of production orders. Now client want the quantilty blockage for the raw material consumption in the order.
I know through availabilty control i can block the cost consumption.
Over here client want for a particuler production order the raw material quantity as well as the cost shud be blocked at wbs level.
ex raw material-- 2000kg and budget for production order -
5000000
so do we have any concept for the same?
Regards,
Kamal Rana
Wrong forum - this is the Basis forum here.
Please close here and create a new forum entry in the MM area
Markus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Done...Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
need to place it in t he right forum.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
10 | |
10 | |
9 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.