Hi PS Gurus,

I have defined budget for my project. Now in the project structure whenever i am assigning activities (interna /external) it is checking the budget. During the assigment of components to the activity it is not checking the budget if that material is a stock item(L), but it is checking the budget if that material is a non-stock item(N). Is it a standard functionality?

Can we also made it to check the budget for the stock items also?

In case of the stock item it is not comming as an assigned cost in the budget/plan/actula/commitment report.

thanks,

Devdut

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Go into transaction OKKP and check wheather Commit. Management is active or not ,

if not then choose component active and save