on 02-06-2009 12:06 PM
Hi,
I have created a WBS from IM-PS Integration. When i am releasing this WBS element, AUC is getting created. I understood and seen in system that when this WBS is settled fully in CJ88, a fixed asset is getting created and i can view the details of that asset also in AS02. After which the settlement rule will also get updated as Fixed asset for this WBS element.
This can also be achieved by manually defining the settlement rule for this WBS element.
Which is the suggested approach?
In my case, i want some of the cost of this WBS to get settled against the cost center and remaining against the fixed asset. Is there any provision to create such settlement rule automatically with the above scenario.
Waiting for reply please.
Thanks
System can generate settlement rule automatically with reciever as cost center by configration of strategy for WBSE settlement rule. system can also generate settlement rule for AUc when u run first settlement. But to distrubute WBSE cost to cost center and AUC, you should do manually.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
yes it is possible
use partial settlement approach and settle to cost centre certain costs based on allocation and source structure configuration
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.