Hi,
I created a external activity (Requisition no is generated). Using this Req no I created PO (invoice plan based PO).Then I confirmed the activity and the PO is also Invoiced.Now if I try to CLOSE the activity
i face a error message saying "Balance of NWA is not Zero".
can any 1 help me?
this is because the cost of procurement is still on the netrwork
you need to settle
if you do want to settle thne cahnge settlement profile to settlement not mandatory
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I think yes, it will affect.
For external activity or service activty,if an invoicing plan has been maintained, the values in the periods are set as specified in the invoicing plan.Otherwise, the activity value is set in the period of the latest activity start date.
The invoicing plan has priority for the values. If no invoicing plan has been maintained, the system
determines the price from the purchasing info record or the activity value.
Also in the case of externally processed activities and components procured externally, invoicing plan including payment conditions are used - or, where there is no invoicing plan, the delivery dates including payment conditions are used.
Regards
Tushar
Mark the delivery completed in PO for service activity.
Sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.