CJ38 Budget Return in Project

Former Member
0 Kudos

Dear All,

Please expalin this trx. CJ38- Budget Return in Project

Regards,

Vishal

Accepted Solutions (1)

Accepted Solutions (1)

Former Member

It allows you to return unused budget on a WBS element to the top level WBS element in the project thereby increasing the distributable amount in the project. This can be used when the activities against a WBS element have been overbudgeted for example.

Regards,

Kenneth