Hi all ,

When i am doing SNP PLORD to PPDS Order Conversion which is scheduled in

Background thru Process Chain i am getting the following message. It seems some Some SNPPLORD are not Converted into PPDS Orders.

The message is Number of pegging areas with planning termination: 4

How to analsye the error. Request some help regarding this.

Thanks,

nandha

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Nandha,

Please check on the following.

1) Check on the activity relationship in PPM whether all operations, activities are connected properly.

2) Just check in sm12 whether any lock during planning run. If any, clear the locks and then retry the planning run

3) Also check whether planning file entries are created for all location products using transaction /SAPAPO/RRP_NETCH

Regards

R. Senthil Mareeswaran.

Answers (1)

Answers (1)

maheshbabu_mg
Advisor
Advisor
0 Kudos

Hello,

Have you tried checking the log in /sapapo/rrplog1.

Regards,

Mahesh