Regarding PIR Reduction's from R/3 to APO

Hi - Please help me with the below issue !!

When a PIR is reduced (withdrawn) in R3 as a result of backflush goods issue, the corresponding PIR in APO does not reduce but it is fine with R3. Please let me know if any configuration settings are missing at APO level.

Any suggestions will be much helpful.

Please let me know if any further info is needed .

Thanks a lot!!

Pullaiah.

Former Member
Former Member replied

Hi,

Do you have a strategy maintained in demand tab of location product master in APO?

The main factors that decide consumption are the assignment mode and the check mode in location product master that come from the strategy group in MRP3 tab of ECC material master. Check your strategy group.