Hello All,
I have a requirement from client where I need to activate the Budget control (90% warning and 100% error). I have done the setting accordingly.
Now the scenario is such that when client is doing budgeting, they are allocating the budget only at top level WBS (they have a different legacy, where they are doing there detail planning n budgeting, but since they want the feature of budget control in PS, they will do minimal budgeting in PS). As per my settings when I budget top level WBS and save the availabity control is activated (with no budget on lower level WBS). Now when I try to do some postings/or assign that WBS to PO, even with a value of 1 USD, i am getting an error of budget exceeded, which is fine as per the settings as that WBS is having 0 budget.
The requirement from client side is such that they want AVAC to be activated only at top WBS and do postings to lower WBS. But if the total of lower WBS exceed the budget of top WBS, they should get an warning or error. For example:
WBS level BUDGET ACTUALS
1 100
2 50
2 50
so as soon as the actuals touch 100, the system should give an error/warning. Note that the 2nd level WBS are not budgeted in SAP, so budget is 0 on them.
I have 2 questions:
1.Is it possible to activate AVAC only for top WBS ?(without any enhancement/development)
2.How the AVAC will work, if the total of 2nd level WBS exceeds the budget of top WBS (as explained in example above)?
Awating your replies.
Thanks
Sarang
Thanks Virendra, it was useful.
I tried other way round also i.e. by not marking the release tab in OPS9 and activating AVAC in CJ30.It works in that way too.
For my other question, regarding activating AVAC only at top level, we can achiebve that by using transaction control in user status.
Thanks
Sarang
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
this is std in SAP
do not distribute budget to lower levels and do use the budget release functionality
modify the budget profile accordingly
this way when you raise a PO on lower level it will heck the budget on the WBS - if none distributed then it will go the parent WBS and check against it
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.