on 02-05-2009 12:34 PM
We are having one problem, For one particuler plant deliveries are creating before delivery date, and it's skipping some deliveries/customers due earlier.
For example: we have four sales orders 1, 2, 3, and 4.
*For first sales order system given*
Transportation plan date: 06/15/2008
Material available date: 06/15/2008
Loading date:06/15/2008
Goods Issue date:06/15/2008
Delivery date is:06/16/2008
Route is: 1 day.
*For the second sales order system given*
Transportation plan date: 06/18/2008
Material available date: 06/18/2008
Loading date:06/18/2008
Goods Issue date:06/18/2008
Delivery date is:06/19/2008
Route: 1 day.
we are creating deliveries in Background JOB, the system created delivery for second sales order before the delivery date:06/16/2008 before materil availability date, How it's posible? and it's skipped the first sales order. for the first sales order delivery was not created, first sales order delivery date is 06/16/2008.
Thanks
Rao
an
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
\Whenever you close your threads with "Answered", please make it as a practice to update the forum as to how you have solved.
This will others in many ways. Hope you will consider this.
And it shows that you have never bothered about check your threads
just today you have got some issue and when you tried to post it had given u a message that close u r earlier threads
So immediately u have closed all u r open threads
thanks
Not Resolved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Resolved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.