on 02-03-2009 1:40 PM
Hi everyone,
Our SRM Production client is copied to SRM Test client.. Now i need to make the test client's configuration again ( integration with r3 , material replication , vendor replication... )
But in the test client, all master data is the same as in the production and for master data, backend system is R3 production client.. I need to replicate all master data, product categories, hierarchy.. again for R3 test client and remove the others (master data came from R3 production).. how should i do that ? which way should i follow ?
Thanks,
Hi,
There are some documents about system landscape copy.
http://service.sap.com/instguides
https://service.sap.com/sap/support/notes/995771
Regards,
Masa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please refer the below document:
https://websmp204.sap-ag.de/~sapidb/011000358700000310782007E/SRM50_SetupTranspCopy.pdf
Regards
Kathirvel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You do not need to replicate all data again, if the same data is existing in your backend system for the Test client. Just ask your basis team to run BDLS txn in the test client system which would adjust the production backend system to the test backend system. Also ask them to create RFC destinations to new backend system.
Also check 'Define backend systems' setting in your test client. You would need to modify it manually to new values.
Regards,
Sanjeev