on 02-03-2009 11:59 AM
Hi,
When i try to set default values for a inspection type in customization, it throws error "Assign a task list usage to inspection type in Customizing"
can anybody help me how to customize the same?
VRMP.
Dear VRMP
First define the task list usages in
SPRO > QM > Inspection planning > general > define task list usage
Then assign the usage for inspection type
SPRO > QM> Quality inspection > inspection lot creation > maintain inspection type
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi VRMP,
As Gajesh pointed out, you need to first define TaskList Usage at location, SPRO>QM>Inspection Planning>Define Task List Usage and then assign it at location SPRO>QM>Quality Inspection>Maintain Inspection Types.
This will solve your problem.
Thanks,
RKM.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.