Assigning Tasklist usage to the Inspection type

Former Member
0 Kudos

Hi,

When i try to set default values for a inspection type in customization, it throws error "Assign a task list usage to inspection type in Customizing"

can anybody help me how to customize the same?

VRMP.

Accepted Solutions (1)

Accepted Solutions (1)

former_member186399
Active Contributor
0 Kudos

Dear VRMP

First define the task list usages in

SPRO > QM > Inspection planning > general > define task list usage

Then assign the usage for inspection type

SPRO > QM> Quality inspection > inspection lot creation > maintain inspection type

Regards

Gajesh

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi VRMP,

As Gajesh pointed out, you need to first define TaskList Usage at location, SPRO>QM>Inspection Planning>Define Task List Usage and then assign it at location SPRO>QM>Quality Inspection>Maintain Inspection Types.

This will solve your problem.

Thanks,

RKM.