An old maint plan having one maint item ..now want to add one more item to that plan but with different task .

And i want after scheduling only the new maint item to be scheduled . Is it possible..

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member187991
Active Contributor
0 Kudos

hi

while adding the new item ,delete the assignment of the old one from the maintenance plan

regards

thyagarajan

ajaysingh_daheriya
Active Participant
0 Kudos

But company need the history of the old plan and respective orders.

former_member187991
Active Contributor
0 Kudos

hi

then create the separate maintenance plan with another maintenane item and do the rest of process.

if you add another item also since the scheduling paramters are same for 2 maintenance item it will create the call objects for the both the items

Just deactive the previous maintenance plan

regards

thyagarajan