Transfr dates from child network to parent network(using subnetwork functio

Former Member
0 Kudos

Hi All,

i have created 2 separate projects one is parent with 1 network activity assigned to root wbs element and other is child project with several network activitites. By using sub network function i have assigned the parent project network activity to the child level project network in Sub netorwk field.

How can i roll up the child projects network dates to parents project network.

Regrds

saqib usman

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

this can be done by scheduling

Former Member
0 Kudos

i have already done sheduling but basic dates are not updating across networks.

how can i scedule two networks in different project at one time.

Former Member
0 Kudos

Try transaction CN24N, in this overall scheduling of selected networks can de done.