on 02-02-2009 4:24 PM
Hello guys,
I have a situation here:
I have only one Warehouse # 200.
I have two Slocs:
Sloc:0001 linked to WM:200
Sloc:0002 works at the IM level.
I have two shipping points (0001 & 0002) for each Slocs as well.
WM:200 sends the goods to both Slocs.
We run VL10G and then VL06P.
The issue is to ship out the Sloc 0002 goods before than the Sloc 0001.
However it doesn't occur at all.
0001 gets the picked items first and if there is any left over quantities then Sloc 0002 gets the rest.
What would be the best Expert approach to make this happen?
Any thrown idea will be appreciated greatly.
Best regards,
Bodik
Hi,
Please check what all storage location you have assigned as picking location.
Regards,
Prashant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.