Hi,
When I create PO from PR in SRM in classic scenario the system gives the messgae as below:
Purchase order has not been created
Pls advise.
Thanks,
Manu
Was the system able to use the sourcing ?
any Vendors assigned?
Arshad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Manu,
Do you mean that you are creating a PO from Shopping Cart? Right!
If you are creating a PO from Shopping Cart then it automatically gets created in the Backend system as soon as the Shopping Cart Gets approved.
Can you please check whether shopping card is approved and completed and also have you done the relevant configurations for that.
Regards,
Sachin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please let me know what all config needs to be done to transfer the PO to backend system from SRM.
We have transferred PR from MM to SRM and created bid and then want to create the Follow-on doc in MM as PO. However, when I create PO as A foolow on doc the system is anot allowing to create PO and gives the message PO has not been created.
Pls advise.
Thanks,
Manu
Hi Manu:
You can transfer any External Req if its permitted in those two tables in ECC whether its account assigned or not.
Did you monitor RZ20 to find out any possible errors? Sometimes, if the PO does not find suitable org structure (Plant, Purch. Organization, Company Code) it fails.
Regards,
Ashok B Kawa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.