is there any way to schedule different group of projects i.e combination of 2 child and 1 parent projects. i want to rollup the child dates to the parent projects for actual/plan values.
i have also attached the sub networks to the child projects network with control paramenters
Control key "blank"
Copy dates "3" Earliest start and latest finish
kindly help so points can be awarded
regards
saqib usman
I have tried CN24n for network scheduling. An errors occurs
No order corresponds to selection criteria
Message no. CO176
Is there any setting required to use that transaction.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Like Nitin has mentioned, you can use transaction CN24N and you can select the networks that you want to schedule in the project.
Confirm the activities and gather the actual dates using bottom up scheduling scenario and once you complete this you can perform scheduling for whole project to extrapolate the dates to WBS elements, eventually you can get the updated dates. Dont forget to maintain the relationships between the activities in appropriate way while using multiple networks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check with txn CN24.
Also CN24n is intended primarly for companies that work with a large no of multilevel sub netwrok structure and don't always want to schedule all networks and sub networks at the same time...
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.