Can the project defination be changed once created

Former Member
0 Kudos

Dear All,

Can the project defination be changed once created.

If Yes, then how.

I have a case where the project defination and its wbs have different initial codes.

For Instance Project Def is T.09.CXX.400

And Its WBS is T.08.CYZ.500.001

How could this happen ?

Please explain

Regards,

Vishal

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks All

nitin_patoliya
Active Contributor
0 Kudos

Yes you can change the PD once created than after. It is based on indirectly OPSK , OPSJ settings.

Always define required coding maks in OPSJ and tick the edit indicator in OPSK... so, than after system will alllow you to change th projec coding mask for the defined coding mask...

If you stricly wanted to not to allow the P.D. after your creation this can be achieved by user status.

Regards

Nitin

Former Member
0 Kudos

Hi,

Thanks for your reply.

But, I found that we could change project def. through transcation CJ07.

Further it is also observed that no change log is maintained for this Proj. Defination change.

I mean to say that , i was not able to trace this change from the system.

Is their some other provision to track these changes.

Regards,

Vishal

nitin_patoliya
Active Contributor
0 Kudos

You can track through CN60 there give your P.D and execute.......

Make sure that for your P.D. the project profile you have used for that project profile you have ticked change document in OPSA txn.

Regards

Nitin

Former Member
0 Kudos

Hi Nitin,

I had ticked the change doc. in project profile through OPSA txn.

Then I had created a project under that project profile.

I also changed the project def.

I tried CN60 transcation to view the change history.

But i am getting the following message .

"No objects were selected using the criteria

entered"

Please suggest, what is wrong here.

Regards,

Vishal

Former Member
0 Kudos

Run transaction CJEN for project.

Sudhir

nitin_patoliya
Active Contributor
0 Kudos

if you have changed P.D. from ABD 10000 to ABC 1000 than while running hte report CN60 you have to give ABC1000 as input in P.D.

Please chekc it should work. I could able to do .

Regards