on 02-02-2009 5:08 AM
Dear all
Plz tell me where we can enter start time and end time of inspection.
Regards
Nirmala
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Nirmala,
PLease check in QA02 of the lot there you will get the start date and end date
Regards
gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nirmala,
I think Inspection start time is not required for any analysis or else. Days taken for closing lots are important than time. Any how, the stock posted or Inspection completed time is already available in Stock posting log - transaction QA33.
In transaction QA33,
1. Input Material, Plant & Period etc
2. Select a lot (UD made)
3. Select Usage decision tab
4. Select Stock posting tab
5. Select Stock posting log in the tab(header) - here your inspection completed (UD) time is getting stored
Further issue, pls reply.
VRMP.
Hi,
You can enter inspection start time & inspection end time for each characteristic during results recording. Click the icon "Inspector, Inspection Date & time" or Menu> Extras>Inspector, Inspection Date & time.
At the inspection lot level we cannot enter Inspection Start & End Times, we can enter only the dates.
With Best Regards,
Vithal