Dear all

Plz tell me where we can enter start time and end time of inspection.

Regards

Nirmala

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

closed

former_member186399
Active Contributor
0 Kudos

Dear Nirmala,

PLease check in QA02 of the lot there you will get the start date and end date

Regards

gajesh

Former Member
0 Kudos

hi gajesh not date i m asking about time

Former Member
0 Kudos

Hi Nirmala,

I think Inspection start time is not required for any analysis or else. Days taken for closing lots are important than time. Any how, the stock posted or Inspection completed time is already available in Stock posting log - transaction QA33.

In transaction QA33,

1. Input Material, Plant & Period etc

2. Select a lot (UD made)

3. Select Usage decision tab

4. Select Stock posting tab

5. Select Stock posting log in the tab(header) - here your inspection completed (UD) time is getting stored

Further issue, pls reply.

VRMP.

Former Member
0 Kudos

Hi,

You can enter inspection start time & inspection end time for each characteristic during results recording. Click the icon "Inspector, Inspection Date & time" or Menu> Extras>Inspector, Inspection Date & time.

At the inspection lot level we cannot enter Inspection Start & End Times, we can enter only the dates.

With Best Regards,