Hi,

How do we analyze the cost factor i.e involved in different maintenance ( planned /unplanned / completed) orders?

Thanks,

K R Vishnu Kumar

Accepted Solutions (1)

Accepted Solutions (1)

former_member260869
Participant
0 Kudos

Hi,

We can analyze the cost factor for different orders by generating the report using the T-code MCI8.

try this & let me know.

Thanks

Arun Vijay D