Problem with project settlement

Former Member
0 Kudos

Hi,

I want to settle cost in project system by exclude some cost element for example

Cost was posted against WBS Y.001 with 2 lines item. cost element 10001 - 100 usd

20001 - 200 usd

Our requirement is only cost element in range 10000-19999 can settle to cost center, for other cost element cost remain in WBS.

But when i excecute project settlement system generate error message as u2018Cost element 20001cannot be assigned to a settlement cost assignment in allocation structure ZGu2019. For allocation sturture ZG i was maintain cost element in source form 10000 - 19999

So, Is it possible to settled by exclude some cost element even cost have posted to?

Thanks so much,

june.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Pornat,

Please check Allocation Structure before cheking the Settlement Profile. In allocation structure the sender cost object and receiver cost object is there, pl check it. if u need any inputs then let me know.

raj

virendra_pal
Active Contributor
0 Kudos

you need to check your settlement profile to

May be settled NOT must be settled