What is the difference between Cost Element and Activity Input Planning in cost palnning?
How to select all the Cost Elements at a time in CJR2?
Thanks,
Sana.
cost element planning is for primary cost elements
Activity planning is for secondary cost elements
you can select a range of cost elements or create a cost element group and use that in the inital screen of txn CJR2