Hi,

Wwhen I transfer PR from MM TO SRM via the report BBP_EXTREQ_TRANSFER.the atatus on the queue in MM is Application aborted due to serious problems.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

See these related threads for more pointers;

BR,

Disha.

Former Member
0 Kudos

Hi,

PR is transferred to SRM from MM.but in Carry out sourcing tab when I add the requirenment to my waork area the system gives the error as below:

Movement type for follow-on document missing

Pls advise.

Thanks,

Manu

former_member183819
Active Contributor
0 Kudos

Hi Manu

Did you maintain BWA = 101 attribute in PPOMA_BBP. Check it up

regards

Muthu

Former Member
0 Kudos

Yes I have Maintained the same.

Do i Need to maintain anything in Attribute : Transaction type Create Manually

Thanks,

Manu

former_member206968
Active Contributor
0 Kudos

Hi

Go in txn-SM58 and check if there are any failure logs. You can also check SMQ1 and SMQ2 queues.

Regards,

Sanjeev

Former Member
0 Kudos

No entries are maintained in SM58

former_member183819
Active Contributor
0 Kudos

Hi

Where did you get this error ? check slg1 too.

what about your accounting assignment in PR?

regards

Muthu