cancel
Showing results for 
Search instead for 
Did you mean: 

regarding confirm activites

Former Member
0 Kudos

Dear all,

i want to do appraisal cost and while results recording confirm activites is greyed out and i am not able to record the actual time taken for inspection.while usage decision aslo it is greyed out.

with regards

kumar

Accepted Solutions (1)

Accepted Solutions (1)

former_member186399
Active Contributor
0 Kudos

Dear Senthil

yes you need to assign the QM order before result recording.

here are the setting required for the same

For appraisal cost,

1) Create an activity Type - Labour hours

2) Create a work center and attach the activity type in this

3) Attach this workcenter in the inspection plan

4) Create a QM order in QK01,

5) Put the relevenet datas as inspection type, material, cost center, order type , cost center, profit center

6) execute and assign the orders to the material

7) Do the result recording and save,. you wil get a pop for recording the activity type

Regards

gajesh

Former Member
0 Kudos

Dear gajesh,

Sorry for the late reply.confirm activites appeared and solved the problem.

with regards

t.senthilkumar

Answers (1)

Answers (1)

former_member186399
Active Contributor
0 Kudos

Dear Senthil

Please make sure that you have maintained a work center which includes activity type and cost center in the inspection plan. also qm order is assigned for the material.

Regards

gajesh

Former Member
0 Kudos

Dear gajesh,

Before making the results recording itself , we have to assign the qm order.please clarify and also how to define actual costing variant.

with regards

senthilkumar