Hi,
I am facing typical problem. Against the WBS budget report is showing the budet available, but when creating PO system is throwing erroe "budget exceeded". I checked PO value which less than available budget.
I run CJBN, CJEN but after that also same error,
Kindly provide your valuable suggestion.
in eroprt parent wbs available budget is not shown seperately it a toal of self + lower WBS available budget.
After checking with distributable value of PO a/v assigned WBS problem is solved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi...
Are you assigning the budget from IM or directly from PS?
If your asigning the busget from IM you need to check if the budget is the same in bouth modules.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Pradeep,
Check this thread once.I faced the same problem and was able to solve it with the reply given by Muraleedharan...refer this thread and check out the note that Muraleedharan has mentioned in his reply.
I am sure your problem will be solved..Hope you are using ECC 5.0. Do let me know about the outcome.
Thanks & Regards,
Gokul
Kindly check this thread
If you have maintained the activity group "++" in the tolerence limit for the AVAC.
then the PO value is also included in addition to PR.
There are two options:
1. Either increase the budget or
2. Note: 955107
Go to OPS9 In the Budget profile which u assigned to ur project, Check for Availabilty control parameters over there Overall Paramaters should be ticked. If not then make it selected.And reconstruct availabilty control thru CJBN then try out ur posting
check this Sap Note: 178837
Hope this will solve ur issue
Regards,
ANSAR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
which tolerance limit you have set, give in detail.
Sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check ur PO's document date and the year in which u r doing budgeting.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Please check any other assigned values are there with reference to WBS or Network (Planned Values)
this can be seen in the CJ31 enter Project Definition --> Extras --> Availability Control --> analysis
check there assigned values either Category 21 or 22 exist or some other value category exists.
Edited by: AP on Jan 29, 2009 9:59 AM
Dear,
You need to check if there is any advance payment to vendor,or down payment to vender for any
PO.
If there is any payment it should be against the PO line Item.
If it is not against the line item then it reduced from commitment value for all line item .
And it is come back to commitment value after GR.
Sukhveer.