on 01-29-2009 2:57 AM
Hi Gurus,
Could anyone kindly tell me what are the integration points of PLM and PS. I know one is assigning DMS documents, what can be other integration points.
Thanks,
Sachin
If you are using ECC6.0 than, you can check this is one of the features which is purely realted to PLM.
-
Tcode CJ20n/CJ01/CJ11/CJ27 (Create/Change/Display)
New Features
u2022cProjects
u2022Integrated Product Process Engineering Tab
Requisite Configuration Settings for iPPE
Path :
SPRO> Project System>Structures>Operative Structures>Work Breakdown Structure -->Create Project Profile
SPRO >Project System>Structures>Operative Structures>Networks>Settings for Networks>
Maintain Network Profile
SPRO--> Project System >Material> Integration of Project system with iPPE-->Define Reference points for the Integration of the Project system with iPPE
Usage:
cProjects
u2022Work Overview & Selection list
u2022Self Services for creating and editing project objects
u2022Communication via email
u2022Assigning Resources to Project objects
u2022Confirmations & Reports
Integrated Product Process Engineering
Transfer of Product Structure from Integrated Product Process Engineering to Project systems via iPPE nodes to Project definitions, WBS Elements, Network activities by means of a reference point.
-
Apart from above we can say partly SPRO>PS> Collobration
cFolder / cProjects
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.