Hi Gurus,

Could anyone kindly tell me what are the integration points of PLM and PS. I know one is assigning DMS documents, what can be other integration points.

Thanks,

Sachin

Accepted Solutions (0)

Answers (1)

Answers (1)

nitin_patoliya
Active Contributor
0 Kudos

If you are using ECC6.0 than, you can check this is one of the features which is purely realted to PLM.

-


Tcode CJ20n/CJ01/CJ11/CJ27 (Create/Change/Display)

New Features

u2022cProjects

u2022Integrated Product Process Engineering Tab

Requisite Configuration Settings for iPPE

Path :

SPRO> Project System>Structures>Operative Structures>Work Breakdown Structure -->Create Project Profile

SPRO >Project System>Structures>Operative Structures>Networks>Settings for Networks>

Maintain Network Profile

SPRO--> Project System >Material> Integration of Project system with iPPE-->Define Reference points for the Integration of the Project system with iPPE

Usage:

cProjects

u2022Work Overview & Selection list

u2022Self Services for creating and editing project objects

u2022Communication via email

u2022Assigning Resources to Project objects

u2022Confirmations & Reports

Integrated Product Process Engineering

Transfer of Product Structure from Integrated Product Process Engineering to Project systems via iPPE nodes to Project definitions, WBS Elements, Network activities by means of a reference point.

-


Apart from above we can say partly SPRO>PS> Collobration

cFolder / cProjects

Regards

Nitin