I have a scenario, where I need to have the person responsible field in project/WBS to be pulled from HR minimaster data. My question is there any standrad way of pulling all the data in HR minimaster to tcode OPS6 or do I need to configure all the values manually in OPS6?
Thanks
Sarang
I guess there is no workaround, other then maintaning it manually in SPRO. Closing the loop.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi:
U need to have WORK Centers and ur HR employees data would be assigned to those work Centers.
After Prsonnel Numbers Assignment to Work Center you can call them in Ur Project/WBS.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As per I know we have to do it manually. Please share if someone has other thoughts.
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.