Could someone tell me the difference between CO06 and V_V2. Both seem to be backorder rescheduling transactions.
Thanks
GS
Dear GS,
CO06 - Material - Back order Processing (rescheduling program SAPLATP4)
V_RA - SD Document - Backorder Processing (rescheduling program SAPMV75B)
V_V2 - Execute Rescheduling/ Rescheduling Sales and Stock Transfer Documents: by material
The rescheduling program (SDV03V02) behind the V_V2.
Best Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi GS
*Difference between CO06 and VV2.*_
V_V2 -> It is a Rescheduling process of backorders
CO06 -> It is also backorder processing but based on material .
Regards
Srinath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.