on 01-28-2009 12:54 PM
Dear PS Experts,
In a Project, I created a reservation of 5 units of item A. Then I issued 2 items against the reservation.
Later on I tried to change my reservation requirement quantity to 6 and SAP allowed it. Then I changed the same quantity to 1 which is below the issued quantity even that was allowed.
My question is why are the above changes allowed after material issue takes place ? (is it a common business requirement)
Else, is there an SPRO setting where we can restrict the above?
Cheers
Deepal
There is a setting in SPRO where you define a Modification Profile and this is asigned to the network, you can find it in Operative structure > Network menu.
Just be careful, this changes will afect all the network's with the profile you are changing.
Best Regards...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
That is the standard SAP functionality only. This is not a strange behaviour of the system. If you create any reservations manually, the system will allow to change at any point of time. While creating the production order or MRP created planned orders will create the reservations. That reservations you can't change.
Regards,
V. Suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.