Hi gurus,

The activity 0050 of network 4006650 created automatically a Purchase Requisition.

Now this Purchase Requisition has to be deleted but the system doesn't allow to delete it via standard ME52 (or ME52N) --> Error message: 'This item is only deletable via the associated production order'.

As said, the 'associated production order' is item 0050 of network 4006650.

The problem is that if we try to enter transaction code CJ20N, select the activity and click on the delete button the system displays a new error message:

'Activity 000004006650 0050 has been assigned material components - Deletion not allowed'.

Could you please let me know how are we supposed to delete this Purchase Requisition if this doesn't seam to be possible neither via me52n nor via cj20n?

Many thanks,

Marc

Accepted Solutions (1)

Accepted Solutions (1)

former_member845166
Active Participant
0 Kudos

hello marc,

first delete the material component asigned to activity

Former Member
0 Kudos

Hi all,

Many thanks for the answers.

I tried to delete the components (they are 2) and the system shows a new error message for each one of them:

'There is still a purchase order commitment for NWA 4006650 0050 0060'

Message no. KO447

Where can I find this PO? This sounds really strange to me as the PR has no PO associated...

Thanks!

Marc

Former Member
0 Kudos

you can check the related PO in report S_ALR_87013558.

In that click on Commitment and then on call up report.

you will get the PO number.

Regards,

Nitin

Former Member
0 Kudos

Hi Nithin,

Which of the following database profiles should I select?

000000000001 Standard selection (structure)

000000000002 Standard selection (profit center)

000000000003 Standard selection (cost center hier.)

000000000004 Standard selection (summarization)

000000000005 Standard selection (cap. invest.program)

000000000006 Standard selection (sales view)

000000000007 Standard selection (standard structures)

SAPMEBPMPS Project Selection for MEB Call in PMPS

SAPMPP000000 Standard Workforce Planning Profile

SAPPS_EV0001 Standard Earned Value Analysis Selection

Thanks!

Marc

Former Member
0 Kudos

select first 0000000000001 Standard selection

Former Member
0 Kudos

OK done. However, I can not see any 'commitment' option.

You said click on 'commitment'... Where is this option? I juts have as selection screen:

Project

WBS Element

Network/order = 4006650

Activity = 0050

Materials in network

Plan version = 0 (Plan/Act - Version).

Were can I see the commitment option?

Thanks,

Marc

Former Member
0 Kudos

Check in CJI5 (Commitment) report.

Former Member
0 Kudos

OK thanks to all,

Now I have found the PO... Should I delete the related items if the PO?

Thanks,

Marc

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

I guess your network is released...In CJ20N... select the material component and then delete... You must be trying to delete the activity...

Regards

Former Member
0 Kudos

I think u r activity status released. Thou u could delete the components first, u wont be able to delete the activity.

This is seems to be SAP standard behavior.

Edited by: VenkatSrinvas Konda on Jan 28, 2009 10:53 AM

Former Member
0 Kudos

Hi Marc,

Does your NWA actually has material components attached to it? If yes then you'll first need to delete the materal compnents one by one and then you'll be able to delete the NWA.