on 01-28-2009 7:08 AM
Hi Gurus,
At the time of usage decision i want to post the material to three different stocks i.e. to unrestricted stock, to scrap & to new material.For posting to new material i give material code & batch number at the time of posting.But scrap is also defined as separate material.When i post to scrap system asks for cost center.As scrap is defined as material i want to post it to a particular storage location.I can do the posting two times to new material and achieve my aim.But i want to do it in a single posting.Is it possible.Is it possible to bring storage location field in front of scrap posting in usage decision screen.
Regards
Amit
Dear Amith
i think you need to do the stock posting twice in QA11 and then in QA12 for scrap material. it will not be possible to bring storage location for scrap.
You can look for option using this user exits :
QEVA0001 Enhancement: Quantity posting for usage decision
regards
gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Gajesh
Thanks for u r reply.
Regards
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.