Appended/Apportioned

Former Member
0 Kudos

Dear experts,

Actually i want to know the scenario. of Appended ......Apportioned

How it works?

I have read in SAP HELP(even though im not confident).

Regards

Chandra

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

When the order/network is appended and apportioned the cost on the network will get added to total planned cost of the WBS (concerned to that network) also it will reflect in the "assigened" values and will be checked against the budget.

If the order is apportioned only then order plan is not added to the total planned cost of the WBS. In this case you won't be able to see the planned cost in the network.

Regards

Answers (1)

Answers (1)

nitin_patoliya
Active Contributor
0 Kudos

OPSV is the IMG setting for the same. Remaning all is clarified by Hemant.

Regards

Nitin

Former Member
0 Kudos

Dear experts.........................Hemanth....Nitin.

Thanx for your inputs.

I have rewarded points.