Workflow terminologies

Former Member
0 Kudos

please explain about the following terminologies in workflow

1. latest end

2. requested start

3. latest start

4. requested end.

and tell me the step by step procedure.

Regards,

selvamuthukumar.

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Answered

bpawanchand
Active Contributor
0 Kudos

Check this [SAP Help|http://help.sap.com/saphelp_nw04s/helpdata/en/a6/9bacab5f2c11d194a40000e82dec10/content.htm]

and [check this article|https://www.sdn.sap.com/irj/scn/wiki?path=/display/abap/deadline+monitoring]

saumya_govil
Active Contributor
0 Kudos

Hi Selvamuthukumar,

The terminologies you mentioned are used for Deadline Monitoring in Workflows. This is used to specify when a workitem to be triggered/terminated by the system. These are date and time based activities that trigger when a particular date / time is met.

Please find below the details:

* 1. Latest end*

It is the Latest time of completion of a work item. After this time is crossed the workitem would get logically deleted.

* 2. Requested start*

It is the time requested to start the processing of a workitem.

* 3. Latest start*

It is the Latest time to start the processing of a work item.

* 4. Requested end*

It is the Requested time when the processing of a work item should get completed.

Please refer to the following link for further details:

https://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/303617cf-73dd-2a10-c993-cc630358...

Hope this helps!

Regards,

Saumya

Former Member
0 Kudos

Requested start

Earliest possible time for the start of processing: The work item does not become

visible in the recipient's Business Workplace until this time.

Latest start

Latest deadline for starting processing of a work item

The status of the work item must change from "Ready" to "In Process"

Requested end

Requested deadline for completion of processing of a work item

Latest end

Latest deadline for completion of processing of a work item.

Regards,

PR.

Former Member
0 Kudos

Visit saptechnical site.

Goto Tutorials->workflow

In that there is a Tutorial on Deadline Monitoring..

This should give you an idea how to proceed further.

Regards,

PR.