Confirming actual dates for activities

Former Member
0 Kudos

Hi Experts,

Is there any way to be able to confirm the actual start date of an activity without confirming the actual end date?

Thanks a lot!

Kind regards,

Neil

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

No,

not to my knowledge you have to enter both actual start and actual finish or none of the fields.

Former Member
0 Kudos

Thanks a lot for your answer.

Can I ask...what is the logic on that constrain? I guess there is a reason for this system behaviour...

Former Member
0 Kudos

Hi Neil,

Indeed you cannot confirm just the start of the activity. The way I understand it is that confirmation is helping you to follow the project progress. If you like to have an information on the start of the activity, you could confirm it partially at the beginning. It will go into status PCNF - Partially confirmed. After the work is done, you may create a final confirmation by ticking the relevant field & update the end date + working hours.

I hope this helps,

Cheers, Aleksandra

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi neil,

How can u expect to conferm with out giving last date of activity. After completation of the logic then only u have a chance to confirm, if u want to complete then u need that last date of the activity.

say thanks in the way of points

thanks

raj