Hi,

I am doing log entry for equipment like Breakdown, idle, maint. working hrs, shift hrs etc.... through IK22 but i want to validate it for 24 hrs, means all additions of breakdown, maint., working , idle hrs has to be 24 hrs.

How can i do this suggest me if it can be.

Thanks in advance,

Vishal

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

can you explain your requirement clearly, what are you trying to validate

regards

thyagarajan

Former Member
0 Kudos

When measuring point updation for working hrs counter system take counter reading more than 24 hrs in one day. i want to avoid it till. it shouldnt take more than 24 hrs.

Thanks,

Vishal

Former Member
0 Kudos

hi vishal,

you are using chracteristics unit in hours so it would not compare in day i guess... try to change the no of characters in CT04 for the characteristic you are using in measuring point and check...

regards