Hi folks

I have quotaion where i get two schdule line items showing

Date format: Delivery date : order qty: rounded qty: confirmed qty:* schedule line category:

D: 26.01.2009 : 1 : 1 : 0 : BN

D 28.01.2009 ; 0 : 0 : 1 : BN

I need same day confirmation of quantity, instead of the above

could you please let me know the configuration points.

ie.

Date format: Delivery date : order qty: rounded qty: confirmed qty: schedule line category:

D: 26.01.2009 : 1 : 1: 1: BN

More rewards for your valuable suggestions

Thanks

Edited by: sap sdcon0 on Jan 27, 2009 3:09 AM

Edited by: sap sdcon0 on Jan 27, 2009 3:18 AM

Edited by: sap sdcon0 on Jan 27, 2009 3:19 AM

Edited by: sap sdcon0 on Jan 27, 2009 3:20 AM

Former Member
Former Member replied

Hi

As far as my knowledge goes, as your Scheduling category is BN(No MRP), availability check is not done.

So, the probable reason could be, you have maintained the Loading time and transportation time in Routes as 1 day each, hence the system is confirming the dates after 2 days.

Check your customizing setting for Routes.

You can check in the quotation that is created, in the overview screen, u can click on Shipping tab, you can see the loading date.

Regards

Vamsi Javaji.