Hi,

We have a issue where even though the contract is fully referenced, its in the being processed status.

How can i configure it to be complete when its fully referenced?

Thanks

Keshini

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Keshini,

In VTAA at item level check whether you have maintained field "Update document flow", this should be X.

Regards,

Abhee.