ATP check based on production finish date

Hi all,

customer order goods for the 02.06.09.

Transportation take 10 days so, by itinerary , I'll have the material avaiability date for the 15.05.2009.

All' it's OK.

Mrp planner , based on customer calendar, insert demand for customer date 02.06.09

We have insert 10 days on material master as Goods receipt processing time, this for anticipate the end of production 10 days before .

Now we need that atp check production order date not including the Good receipt processing time

Is it possible ?

Regards

Sil

When I do atp check by sales order , ato check see the 02.06.09 as avaiability date and not the desidered 15.05.09

Any idea about haw to realised atp check on