hi everybody,

can any one tell me how to make a billing plan,

thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

In SAP SD a billing plan is a schedule of individual billing dates for a single item in a sales document. You can define a billing plan at header level, which is then valid for all items assigned to it.

Depending on the kind of business process you are carrying out, the system can automatically propose one of two different types of billing plan: periodic billing or milestone billing.

u2022 Periodic billing means billing a total amount for each individual billing date in the plan. For example, if you are creating a rental contract, the system can propose a schedule of monthly rental payments, according to the length and conditions of the contract.

u2022 Milestone billing means distributing the total amount to be billed over multiple billing dates in the billing plan. For example,you can use a billing plan for billing a make-to-order item that is assigned to a project in the SAP Project System. When you enter the project-related make-to- order item in the sales order (or assembly order), the system proposes a billing plan based on milestones defined for networks in the project. As each milestone is successfully reached, the customer is billed either a percentage of the entire project cost or simply a pre-defined amount.

For customization details please go thru following links.

http://help.sap.com/printdocu/core/Print46c/en/data/pdf/SDBIL/SDBIL2.pdf

http://www.sap-img.com/sd006.htm

Regards,

Abhee.