Distribution of work over duration

Former Member
0 Kudos

Dear All,

In my present set up, when i distribute the work over the duration of the activity, the distribution is linear.

Ex- 50 m3 of excavation in 5 days will get distributed as 10 m3 daily for 5 days.

How can I make the distribution variable ( S-curve, or sinusoidal etc)???

Regards,

VikasDev

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Vikas,

To use a custom distribution key you need to make configure the following:

Navigate to the following node in SPRO:

Project System > Resources > Distribution

1. Distribution function - tcode OPB2

The following data is for a S curve distribution. you can use MS excel to distribute % Req values according to the curve equation you want.

% Dur % Req

10 2

20 5

30 12

40 27

50 50

60 70

70 83

80 92

90 97

100 100

2. Use the distribution strategy that you want to use, normally the standard SAP strategies suffice almost all requirements.

3. Create a new Requirements Distribution key

Use the Startegy decided in number 2 and function from number 1.

You are ready with your S curve distribution key.

Let me know if this helped.

jibat

Edited by: Jibat Sankar De Sarkar on Jan 24, 2009 12:14 PM

Former Member
0 Kudos

Grt...thanks Jibat, this will definitely work.

Can u tell me where can i see the distributions in a trend or graphically or in some bar chart

for the activities.

Regards,

VikasDev

Edited by: Vikasdev Sharma on Jan 25, 2009 7:48 AM

Edited by: Vikasdev Sharma on Jan 25, 2009 7:49 AM

virendra_pal
Active Contributor
0 Kudos

you can see in project planning board

txn CJ2B

select activity and click on capacity overview button

in the bottom window select work centre, right click, load as histogram etc