Is it mandatory to complete the loop from starting to the end or can one keep two or more open ends? That is will it be ok with the scheduling process?

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

good practive if scheduling is to have a loop where only activity has no predecessor and one activity has no successor