on 01-23-2009 12:06 PM
Hi Gurus
After running Transaction CJ8G (Settlement Run), then I log into cProjects, locate my Project and go to the Accounting Tab, I click on Calculate, then Save, then I return to the cProjects Dashboard
When I look at the Actual Costs Value it is zero.
What do I need to do to prevent this from happening?
My overall process is.
Approve Time: CATS_APPR_LITE
Send Confirmed Time to cProjects SE38 - (DPR_CATS_CPR_TRANSF)
Transfer Timesheet Data to Controlling CAT7
Log in to cProjects
Locate the Project in question and go into Accounting
Click on Calculate & Save
Click on Home (Actual Costs > 0)
Generate Settlement Rules CJB1
Execute Settlement Run CJ8G
Log in to cProjects
Locate the Project in question and go into Accounting
Click on Calculate & Save
Click on Home (Actual Costs = 0)
Many Thanks in advance
Panduranga
Many Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Panduranga,
The Badi OLR3_COSTS introduced with the note
1095514 enable you manipulate the costs showed in the dashboard. Please take a look the longtext of the note and implement (very simple) the codes.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
3 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.