Hi,
Is scheduling necessary, can't we put dates manually in networks and wbs?
Thanks!
scheduling is not necessary
it depends on the requirements
scheduling is an available functionality in SAP PS which you can use if required
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
planned dates are automatically calculated by the system, this determination of the planned dates of networks is called scheduling as per my understanding.
now i want to know that can't we put these dates manually and not automatically ?
assume that we are not calculating float. then also is it necessary?
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Scheduling is very much necessary my friend. Otherwise how does system calculate Float?
You have to carry out scheduling & that's the standard practice.
Regards
Amaresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.