on 01-23-2009 7:31 AM
Dear All,
Mention how to run MRP in MTO scenario of Project based Production industry.
run the MRP by PP or PS?
if we runs the mrp by ps then there will be problem for the material consumption
and if run the mrp by pp then mrp will be based on sales order, not by project name.
pls. suggest .....
Thanks.....
mrp in MTO scenario should be PS based - best practice approach
run MRP after assigning material requirement to PS activity
this should create planned order to fulfill requirements
convert planned order to production order
material for production consumed in production order
finished or produced goods issued to PS activity for consumption