I have transfer some material in one location (1000)

Now same materia I wants to transfer to APO's defferent location (6000)

I have material master in R3 for the same material in plant 6000

I have tried by CIF through job but it is not updated

what could be the reason

Thanks in advance.

Regards,

Nilesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Nilesh,

Please check on the following.

1) Check whether location 6000 master data in R/3 is maintained properly

2) You need to transfer location 6000 to APO before transferring the material

3) You need to maintain R/3 master in all respects for location6000 for that product before transfer

Please check these and confirm to me.

Regards

R. Senthil Mareeswaran.