Hi experts,

When am creating delivery document which contain 2 line items

1 line item having delivery date 23.01.2009

2 line item having delivery date 23.02.2009

Both are confiming delivery on the date of 23.01.2009 what could be the reason why it is happening

in schedule line material cofirmation date is 23.02.2009 but it is getting confirming todays date.

thanks in advance.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member217082
Active Contributor
0 Kudos

Hi

In MM02 check wheather you have maintained RLT days , GR time or not

In VOV8 check wheather you have maintained Lead Time in Days or not

In OVXD check wheather you have maintained Picking time , packing time , Load Time

If you keep all these feilds blank then the delivery date will be same date as the sales order creation date

Regards

Srinath

Former Member
0 Kudos

Hi,

check the second line item Scheduling in MM02

In house production days

Planned delivery time

Whether you might have maintained days .

Regards,

Reddyy