on 01-23-2009 3:47 AM
Hi,
Can anybody explain about pre encumbrence of shopping cart for Public sector in SRM.
Is SRM 5.0 support Pre encumbrence?
Regards,
Koushik.
Approved and budget checked: Open requisitions (Pre-Encumbrance) / purchase orders (Encumbrance)
Used to control expenditures or revenues against a pre-defined budget.
Pre-Encumbrance is a declaration of intent to set aside funds in the future. Pre-Encumbrance entries are created in the General Ledger, and they post to a special Pre-Encumbrance amount field in the Actuals ledger. Pre-Encumbrances do not affect the Posted Total Amount in the Actuals ledger; they do reduce remaining spending authority as seen on monthly financial reports.
e.g.
BUDGET u2013 PRE-ENCUMBRANCE u2013 ENCUMBRANCE u2013 EXPENSE = AVAILABLE BALANCE
...$200 ..................... $20 ..................... 0 .......................... 0 ..... = ............... $180
...$200 ..................... -$20 -
> $20..........................0.... = ............... $180
...$200 ..........................0 ..................... -$20 -
> $20.... =............... $180
Step 1: A pre-encumbrance is established by entering a requisition.
Step 2: A pre-encumbrance moves to an encumbrance once a purchase order is issued for the requisition.
Step 3: An encumbrance moves to an expense once the items are received and the invoice is paid.
Hope this helps.
Thanks
Ashutosh