on 01-22-2009 1:18 PM
Hi
How can i check who has change the cost center in WBS , or what cost center has been used before the changes in WBS.
Thanks in advance
Hi,
As posted by Sarang CN60 will give you the Change documents for the project.
However your project needs to have a project profile with Change documents enabled in the Basic Data section in the Control tab (tcode: OPSA).
jibat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
CN60 is the transaction to track changes in proj data (Master and other data). This should help you.
Thanks
Sarang