on 01-22-2009 1:10 PM
Dear All,
When i go to accounting view and run calculate following warning comes
No costing variant exists in controlling scenario CPR1
And system does not calculate anything.
1. I have mentioned Cost/revenue rate in one task
2. I have checked entries in CPR1 controlling scenario in SPRO and entry PCO2 exists there for costing variant.
3. Patch level for cProjects 4.0 is 06. due to some reasons cannt upgrade the patch level to latest.
Plesae help.
Thanks In Advance
Niketan
hi Niketan,
Please check as follows:
In costs and activity types assignment when you select cost element and revenue element for your organization unit check cost element category as 1 for cost element and for revenue element, cost element category to be 11.
Also check if both these cost elements and Activity type to be maintained for same controlling area.
Regards,
Niraj Sikligar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Niketan,
Please take a look the my check report, you can copy the codes into a report then run it.
https://www.sdn.sap.com/irj/scn/wiki?path=/display/plm/cprojectCustomizingofAccountingIntegration
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.