Dear gurus,
when i create a PR from cj20n/cn22 with qty and rate and do the PO against that PR. Having created PO against the PR system is allowing us change the data in the PR(like Qty, Rate..etc.).but the requirement in my project once the PR is converted into PO system should not allow us to do any changes in the PR. please help us in controlling this.
thanks
This can not be control by user exit. You have to take Abaper's help to disble the screen qty for modify from enhancement provided by SAP in ecc 6.0. If you have lower version then original screen has to be modified taking sap key for modification
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You will have to do development using exit CNEX0009.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.